Short Tour
Short Tours have been filled to capacity. Thank you for many subscriptions.
‹Shin-Toyosu Substation›
Date: September 8 (Wed.)
Time:
9:30am – 11:30am (morning tour)
13:20pm – 15:20pm (afternoon tour)
Fee: Free
Maximum Attendance: 45 persons (each tour)
Substation Features
- Shin-Toyosu substation is the first 500kV underground substation in the world.
- It was adopted a circular form building to save construction costs. The building is divided into 3 sector parts and equipment is installed in each part.
- It was adopted state-of-the-art Gas Insulated Switchgear (GIS, one-break-point) as 500kV switchgear to improve reliability and save space.
- 500kV power lined are the first long-distance 500kV underground transmission lines in the world (Route length: 40km, XLPE cable).